Report for June 2, 2023

These are the week activities

- We keep installing the roof on B wing
- We finished painting purlins on the library roof structure
- We keep doing stucco on the corridor walls of the B wing
- We keep doing stucco on the outside walls of the A wing
- We keep welding window grills without logo and we have started welding window grills with logo
- We started excavating the trench for the sewer pipes from the administration to the sanitary manhole.
We thank God and all our fellow donors.