ORLEY FORD ADVENTIST UNIVERSITY  CONSTRUCTION REPORT

 May 17, 2024

University

  • Security bars in Library and B wing. Completed

  • Stage of the multiple purpose room. (90%)

  • Drywall in administration offices. Completed

  • Ceiling tiles in administration offices. Completed

  • Concrete Ditches. Completed

  • We are installing ceramic floor in administration offices.

  • We are working in the drywall of the Library.

  • We are installing ceiling tiles in the Library.

  • We are installing the last security bars in A wing.

  • We are laying blocks in bathrooms of the dorms in front of the cafeteria.