Report for January 31 - February 4, 2022






























These are the activities that have been carried out:
Wing 1
- We have tied rebar to make the round column frames for the corridor.
- We have tied rebar for footing frames to continue the corridor.
- We have poured out concrete for the round columns.
- We have painted with primer the purlins to be installed for the roof.
- We have continued working on the roof framing.
- We have finished the demolition of the previous column bases.
Wing 2
- The footing frames have been made.
- We tied rebar and placed the footing frames.
- We have poured out concrete for the column pads.
- We have laid 3 lines of blocks in 32 meters.
We are always grateful for your support.
Happy Sabbath
Construction committee.