Report for January 23 - 27, 2023


























SUPERVISORS:
- Francisco Aguilar: (Superintendent)
-Juan Peñate
-Karla and Yoshi
WORKERS:
- 5 masons
- 3 welders
- 19 tenders
CONSTRUCTION PROGRESS KITCHEN EXTENSION:
- We dug the holes for the grade beam
- We poured concrete for the footing
- We moved materials from the University to the kitchen area.
CLASSROOMS, LIBRARY, SITE WORK AND SEPTIC TANKS
- Excavation of the ditch on the South side
- Excavation of the two septic tanks
- Excavation of a trench to connect septic tanks to the pond
- More area in front of the administration room was scraped and spoils were taken away
- The pedestals of two columns were made
- One column was poured
- The last 3 trusses on B wing were centered on the pilasters
- The stucco in 2 classrooms was finished
- More purlins were welded together to make beams
- Roofers made a site visit prior to the installation of the roof
- The electricians reinstalled the ground line
We praise our Gods for the progress that has been made this week. We request a lot of prayers, so that this project continues to be guided by our Heavenly Father and thus fulfill the mission that God has given us in El Salvador. We look forward to receiving our brothers and sisters from North America in March to work together and recognize that everything has been made possible thanks to the mercies and blessings of our God.
Happy Sabbath! O Lord, come!