Report for February 7 - 18, 2022

The activities that accomplished during this week are the following:
WING 1:
- Advanced 80% with the installation of the purlins.
- Finished the concrete floors of the corridor, up to the offices.
- Continued placing base paint on the purlins.
- Continued the finishes of the welds of the purlins and finishes between the blocks.
- Assembled iron screeds for the office area
WING 2:
- Assembled cylindrical iron columns for the corridor.
- Placed 5 cylindrical iron columns in the corridor.
- Assembled iron screeds.
- Compacted 3 of the first 5 classrooms.
- Laid blocks in the first 5 classrooms at ground level. (ready to start with the walls)
- Placed concrete slabs on the first 5 classrooms.
- Cleaned the first 5 classrooms of useless materials.
We thank God for all the work and progress during this week.
Construction Committee