Report for February 6 - 10, 2023

PERFORMED ACTIVITIES:

KITCHEN EXTENSION:


- The kitchen extension area was compacted
- The grade beam was poured



CLASSROOMS, LIBRARY, AND PARKING LOT:


- The steel grids for the two septic tanks were placed
- We made 70% progress pouring soil cement for the ditch
- Two columns were poured
- Holes for the last two columns were dug out on one side of the library
- Metal plates were installed inside the library and purlins were welded
- Purlins were installed in the computer lab
- Base coat of stucco on the outside of classrooms, up to the last classroom in A-wing
- Site work continues in the parking lot
- The red rock is being compacted for the parking lot
- Various jobs continue to be carried out in different areas


May God continue to bless His children and this missionary project