Report for February 21 - 25, 2022




















WING 1:
- We continued 100% with the installation of purlins up to the initial area of the offices as well as the
concrete slabs of the corridor.
- Also made progress with the base painting of the purlins, continued with the finishes of the purlins,
welds and the finishes between the blocks.
- We assembled foundation screeds for the office area.
WING 2:
- We assembled cylindrical iron columns for the corridor, placed 10 cylindrical iron columns in the
corridor as far as the bathroom area, placed concrete on pedestals up to the bathroom space,
assembled iron screeds, compacted 100% of the first 3 classrooms and 40% of classrooms 4 and 5, and
we laid blocks in the first 5 classrooms at ground level and in 1 bathroom area.
We are thankful to God for all the work and the progress we achieved during this week.
Happy Sabbath!
Construction Committee.