Report for August 17, 2023

During this time, we accomplished the
following activities:
Installation of:
- 24 windows
- 9 doors
- Ceramic floor in 6 classrooms
Elaboration of:
38 security bars (2.17 x 2.17 cm)
10 security bars (medium)
- Excavations to install pipes.
- Installation of sewage pipes.
- First coat and second coat of stucco in
walls at Wing B.
- Manufacturing Windows and doors
frames.
- Cement floor in 5 classrooms.
- Excavation and modification of the
Auditorium floor as requested.
- Transfer of warehouse to Wing B.
- Installation of electrical system in Wing A.